HIGH RISK SPECIALIST

High-Risk Special Work JSASample Guide (7 Types)

Standard risk analysis data for life-threatening high-risk construction.Check images and download the original PDF.

HR-01

Aging Pipe Replacement and Flange Welding Repair

⚠ Critical Hazard Factors

Residual flammable gas explosion, fire from welding sparks

🛡 Essential Control Measures

Verify 0% LEL, isolate combustibles within 11m, and assign fire watch

JSA Report Preview

Aging Pipe Replacement and Flange Welding Repair Preview
HR-02

Substation High-Voltage Switchgear Inspection and Cable Replacement

⚠ Critical Hazard Factors

Electric shock from switch misoperation, arc flash from residual charge

🛡 Essential Control Measures

Implement individual LOTO, verify zero voltage with detector, and discharge grounding rod

JSA Report Preview

Substation High-Voltage Switchgear Inspection and Cable Replacement Preview
HR-03

Excavation and Shoring Installation for Piping Burial

⚠ Critical Hazard Factors

Explosion from underground utility damage, burial due to slope failure

🛡 Essential Control Measures

Perform utility detection and manual excavation, maintain safe slope, and monitor instruments

JSA Report Preview

Excavation and Shoring Installation for Piping Burial Preview
HR-04

Radiographic Testing (RT) for New Pipe Weld Quality Inspection

⚠ Critical Hazard Factors

Radiation exposure, unauthorised entry into controlled areas during night work

🛡 Essential Control Measures

Calculate safe distance and install boundary rope, assign authorised guard, and carry survey meter

JSA Report Preview

Radiographic Testing (RT) for New Pipe Weld Quality Inspection Preview
HR-05

Internal Precision Inspection and Residue Removal of Nitrogen-Purged Tanks

⚠ Critical Hazard Factors

Asphyxiation due to residual nitrogen, isolation in confined spaces

🛡 Essential Control Measures

Forced ventilation before/during entry, oxygen monitoring, and mandatory external watchman

JSA Report Preview

Internal Precision Inspection and Residue Removal of Nitrogen-Purged Tanks Preview
HR-06

Crane Lifting and Moving for Heavy Equipment Installation

⚠ Critical Hazard Factors

Equipment tip-over due to ground bearing failure, crushing by falling cargo

🛡 Essential Control Measures

Reinforce outrigger pads, follow 2-line hitching, and perform 10cm test lift

JSA Report Preview

Crane Lifting and Moving for Heavy Equipment Installation Preview
HR-07

Factory Roof Panel Repair and MEWP (Rental) Operation

⚠ Critical Hazard Factors

Fall from damaged corroded roof panels, electric shock from high-voltage lines

🛡 Essential Control Measures

Install load-distributing scaffolds, double-tie safety harnesses, and maintain electrical clearance

JSA Report Preview

Factory Roof Panel Repair and MEWP (Rental) Operation Preview